Delphi’s Main and Washington construction time may be extended

By Debbie Lowe
Staff writer

It was announced at the Monday evening Delphi Board of Works meeting the current construction on Main and Washington streets may not be finished when initially planned. Street Commissioner Aaron Lyons reported unexpected sub-grade soil issues were discovered as the project proceeded. He said INDOT, the entity responsible for the project’s funding, ultimately changed the scope of the work, which may take slightly longer to complete than originally expected.

Lyons said INDOT may extend the deadline for completion to allow Milestone Contractors ample time to finish the work.

Lyons also said INDOT and Milestone Contractors are making every attempt to finish the work by the end of this week, which was the initial completion date.